UConn Wireless Service Expansion – Project Overview

Description

Wireless network connectivity is a foundational element of contemporary IT services.  This highly visible service impacts not only current members of our community but also visitors and prospective students. Use of this service has grown steadily and will continue to do so as the number of devices per individual and expectations for robust wireless connectivity increase.

Currently less than 50% of University buildings have the quality coverage and sufficient capacity to deliver a contemporary wireless service. The result is an uneven network experience across the entirety of a building and the campus at large. Aging infrastructure and ad hoc deployments for funded projects (e.g., new construction or building renovations) have contributed to this issue.

To improve performance and coverage, the University has made sufficient capital resources available starting the last quarter of FY2017 and continuing through FY2018. With these funds, ITS will strategically augment and supplement the wireless network infrastructure to provide all administrative and academic buildings across all UConn campuses with full wireless coverage.

 

Purpose: Provide our community and visitors a contemporary wireless networking experience that aligns with their expectations for performance and mobility.

Scope: Expand indoor wireless service coverage in academic and administrative UConn buildings on all campuses to ensure quality coverage and sufficient capacity.

Objectives:

  • Provide a contemporary wireless experience by augmenting current infrastructure. This will be accomplished through the installation of new wireless access points in all indoor locations which do not meet contemporary standards.
  • Communicate and coordinate upgrades with building administrators to minimize impact to the community

Funding: Funding for this project is coming from two sources. Expansion of wireless in the Student Union, a student-centric facility, was funded by the Student Tech Fee. Central funding is covering all other university buildings.

Staffing: ITS Network Operations and Physical Infrastructure will be responsible for coordinating and executing this project.

Duration: The project will be completed by the end of FY18 and will be executed in five quarters.

Implementation

As of March 2017, approximately 2400 wireless access points (WAP) were deployed in academic and administrative areas only across the Storrs and regional campuses. To have full coverage in all of the academic and administrative areas, ITS will deploy an additional 2000 WAPs.

ITS will be scheduling upgrades on a quarterly basis. The five project quarters span the following dates:

Quarter 1:  April 1-June 30, 2017

Quarter 2:  July 1-September 30, 2017

Quarter 3:  October 1-December 31, 2017

Quarter 4:  January 1-March 31, 2018

Quarter 5:  April 1-June 30, 2018

The table below lists the buildings that will be upgraded, their project quarter, and the status of the upgrade.

Key:

Completed

In Progress

Upgrade was deferred due to construction.

No network to building.

Building Name Project Quarter Status
A.L. Lorentzen Connector 3 _ 
A.L. Lorentzen Stable 3 _ 
Advanced Technology Laboratory 4 _ 
Ag Biotech Lab Annex 4 c 
AG/Biotechnology (ABL) 1 _ 
Ag-Bio Greenhouse 4 _ 
Alumni Center 1 _ 
Arjona Building (Humanities) 5 _ 
Art Ceramic Studio 2 _ 
Art Design Center (Hall House) 1 _ 
Atwater/Patho 2 _ 
Avery Point Campus 3 _ 
Avian Research Building 4 _ 
Babbidge Library (Homer) 5 _ 
Barnes & Noble 2 _ 
Baseball Field & Press Box 4 _ 
Basketball Development Center 4 _ 
Batting & Pitching Facility 4 _ 
Beach Hall 1 _ 
Benton Museum 2 _ 
Biobehavioral 4 Annex 3 _ 
Biobehavioral Sci Bldg 1 3 c 
Biobehavioral Sci Bldg 5 3 _ 
Biobehavioral Sci Prefab 4 Orig Bldg 3 _ 
Biobehavioral Sci, Prefab 3 3 _ 
Biology/Physics 1 _ 
Bishop Center 3 _ 
Bousfield Psychology Bldg 5 _ 
Bronwell Building (Arthur B.) 1 _ 
Budds Building 2 _ 
Burton Football Complex & Shenkman 4 _ 
Castleman Building (Eng I) 1 _ 
Cattle Resource Unit 3 _ 
Central Warehouse 2 _ 
Chemistry Building 1 _ 
Co-Gen/Heating Plant 2 _ 
College Of Liberal Arts & Sciences 5 _ 
Commissary Bakery & Warehouse 4 _ 
Daily Campus Building 1 _ 
Dairy Barn & Silo 4 c 
Depot - Longley School 5 _ 
Depot- Andover Cottage 5 c 
Depot- Ashford Cottage 5 c 
Depot- Bolton Cttg (Puppet Art) 5 c 
Depot - Brown Building 5 _ 
Depot C - Drl Maintenance Bldg 5 _ 
Depot- Chaplin Cottage 5 _ 
Depot- Colchester Cottage 5 c 
Depot- Columbia Cottage 5 _ 
Depot- Coventry Cottage 5 c 
Depot- Depot D Ct Adv Pavement Lab 5 _ 
Depot- Ellington Cottage 5 c 
Depot- Fuel Cell Institute Building 4 _ 
Depot- Garage 5 c 
Depot- Hampton Cottage 5 _ 
Depot- Hebron Cottage R 5 _ 
Depot- Kennedy Cottage 5 _ 
Depot- Lamoure Hall 5 c 
Depot- Lebanon Cottage 5 _ 
Depot- Manchester Cottage 5 c 
Depot- Mansfield Cottage 5 _ 
Depot- Merritt Hall 5 c 
Depot- Norling Building 5 a 
Depot- Physical Plant/Ct Transport 5 c 
Depot- Sequin Hall 5 c 
Depot- Stafford Cottage 5 _ 
Depot- Surplus Operations (Laundry) 5 _ 
Depot- Thomson Hall 5 _ 
Depot- Tolland Cottage 5 _ 
Depot- Union Cottage 5 c 
Depot- Vernon Cottage 5 _ 
Depot- Walters Cttg 5 _ 
Depot- Willimantic Cottage 5 c 
Depot- Willington Cottage 5 c 
Depot- Windham Cottage 5 _ 
Dodd Research Center (Thomas J) 1 _ 
Drama Music Building 1 _ 
EH&S 3 _ 
Engineering II 1 _ 
Facilities 2 _ 
Facilities  Ops Zone 4 3 _ 
Family Studies 2 _ 
Farm Det Hdqtrs, Hrsbrn Hill Rd 3 _ 
Field House 2 _ 
Floriculture Building 3 _ 
Gampel Pavilion / Sports Center 5 a 
Gant Plaza 5 b 
Gentry, Charles B. (Neag) 1 _ 
Gulley Hall 2 _ 
Hall Building 2 _ 
Hawley Armory 2 _ 
Hi Tech Poultry Facility 4 _ 
Horse Unit #2 3 _ 
Human Development Center 5 _ 
Hydraulic Lab-Eng,Pnk Rav 5 c 
Ice Arena 4 _ 
Information Technology Building 1 _ 
Institute Of Materials Science 5 b 
Jones Building 4 _ 
Jones Building Annex 4 c 
Jorgensen Center 3 _ 
Kellogg Dairy Center 3 _ 
Koons 2 _ 
Landscaping (Old Motor Pool) 4 c 
Law School Campus 3 _ 
Manchester Hall 2 _ 
Math Sciences Building 5 b 
Merle S Klinck Agricultural Enginee 4 _ 
Microchemistry Lab-Prefab 2 3 _ 
Mink Barn 2 _ 
Monteith Building (Soc. Sciences) 1 _ 
Motor Pool 2 _ 
Museum of Natural History 3 _ 
Music Building 2 _ 
Music Library 5 _ 
Nafe Katter Theater 2 _ 
Oak Hall 1 _ 
Observatory - Spring Hill 5 _ 
Pfizer Modular A 5 c 
Pfizer Modular B 5 c 
Pharmacy/Biology Building 1 _ 
Phillips, Dc Bld(Communic Sci) 1 _ 
Physics Building 5 b 
Pit Greenhouse 5 _ 
Planetarium 5 c 
Police & Fire Complex 2 _ 
Polo Arena 3 _ 
Poultry Breeder House 4 c 
Poultry Brooder House 4 c 
Poultry Commercial House 4 c 
Poultry Contest House (Small) 4 c 
Poultry Feed House 4 _ 
Poultry House 2 4 c 
Poultry Teaching House 4 c 
Oak Hill Rd 1 _ 
Press Box - George J. Sherman Family 1 _ 
Ratcliffe Hicks Building 4 _ 
Rosebrooks Barn Rt 195 North 4 c 
Rosebrooks House 5 c 
ROWE (Center for Undergraduate Education) 1 _ 
Schenker Andre Lecture Hall 1 _ 
School of Business 1 _ 
School Of Fine Arts - Art 2 _ 
South Campus Chiller 5 _ 
Storrs Hall 2 _ 
Student Union 1 _ 
Tasker Admissions 3 _ 
Torrey Life Sciences Bldg 1 _ 
UPDC 2 _ 
UPDC Trailer 2 _ 
UTEB 1 _ 
Veterans House 4 _ 
Visitor's Center / Lodewick 2 _ 
Von Der Mehden 2 _ 
Waste Water Facil 2 _ 
Water Treatment (Swg Sta-Wpcf Operations Bldg) 2 _ 
Waterbury Campus 4 _ 
West Classroom Bldg 1 _ 
Whetten 2 _ 
White Building 4 _ 
Wilbur Cross Building 5 _ 
Williams Health Svs 2 _ 
Wood Hall 2 _ 
Young Building 4 _ 

Implementation

As of March 2017, approximately 2400 wireless access points (WAP) were deployed in academic and administrative areas only across the Storrs and regional campuses. To have full coverage in all of the academic and administrative areas, ITS will deploy an additional 2000 WAPs.

ITS will be scheduling upgrades on a quarterly basis.

Quarter 1: April 2017- June 2017

Building % Wireless Coverage Today Status Est. Completion date
PHARMACY/BIOLOGY BUILDING 100% Complete week of 6/16
BIOLOGY / PHYSICS 100% Complete week of 6/5
CHEMISTRY BUILDING 100% Complete week of 6/16
INFORMATION TECHNOLOGY BUILDING 100% Complete week of 6/5
TORREY LIFE SCIENCES BUILDING 100% Complete week of 6/5
ENGINEERING II 100% Complete week of 6/16
BEACH HALL 100% Complete week of 6/16
CASTLEMAN BUILDING (ENG. I) 100% Complete week of 6/16
CENTER FOR UNDERGRADUATE EDUCATION 100% Complete
BRONWELL BUILDING (ARTHUR B.) 100% Complete week of 6/16
UNITED TECHNOLOGIES ENG BLDG 100% Complete week of 6/16
DRAMA MUSIC BUILDING 100% Complete week of 6/5
SCHOOL OF BUSINESS 100% Complete week of 6/5
AG BIO-TECHNOLOGY (ABL) 100% Complete
DODD RESEARCH CENTER (THOMAS J) 100% Complete week of 6/9
STUDENT UNION 43% Scheduled 6/5 week of 6/16

Quarter 2: July 2017 – September 2017

Building
Barnes and Noble (cooperation with BN Contractors)*
Field House/Physical Education
Music Building (w/Orch.Band)
Von Der Mehden Recital Hall
Art- School of Fine Arts
Daily Campus
Music Library
Nafe Katter Theatre
Arjona
Oak Hill Road
Art Ceramic Studio
Whetten Grad Center
Babbidge Library*
Visitor's Center
Co-Gen Facility
Heating Plant
Institute of Material Science
Gulley Hall
Manchester Hall
Family Studies Building
Budds Building
Motor Pool and Vehicle Maintenance
Police and Fire Complex
Facilities Operation Building
Architectural and Engineering Services
SWG STA - WPCF Operations Building
Central Warehouse
Water Reclamation Facility
AES Construction Trailer
Storrs Hall
Koons Hall*
Hawley Armory
Benton Museum of Art
Hall Building
Atwater Lab
Wood Hall
Williams Health Services Building
Human Development Center
South Campus Chiller
Physics Building
Pfizer Modular A
Pfizer Modular B
Mink Barn (Fac Ops Public Works)

* These locations have active construction projects that may include or impact the scope of work.

Locations will be scheduled by quarter, and sequence will be based on several factors including:  need, accessibility, contractor availability, and deployment efficiency. Scheduling for quarters three through five are currently still in development.